A conveyor gallery is designed backwards from the belt. Belt width and speed, material weight, starting and running tension, drive location, walkway width and maintenance access fix the gallery cross-section, the trestle spacing and the support steel. The structure carries the belt, the walkway and the wind load on a long, narrow box — and it has to stay aligned while the belt runs.

  • The gallery span itself, open or enclosed, with a floor for the walkway.
  • Trestles or portal supports carrying the gallery at intervals.
  • A transfer tower where the belt discharges or changes direction.
  • Stairs, platforms and access points to the walkway.
  • Belt support frames, idler bases and pulley support steel if in scope.
  • Chutes, hoppers and dribble chutes at transfer points.
  • Cladding, roofing and drainage where the gallery is enclosed.

Scope lines matter more here than in a building: the belt, the idlers and the drive usually belong to the conveyor vendor, while the structural frame, walkway and cladding belong to the steel package.

Part 2: The conveyor data you must get before detailing

InputProvided byWhy the steel cannot be fixed without it
Belt width and speedConveyor vendorSets gallery internal width and walkway clearance
Material type, bulk density and lump sizeProcess designSets live load, wear allowance and chute angles
Starting and running belt tensionConveyor vendorPulls the gallery and trestle in the belt direction
Drive station location and weightConveyor vendorConcentrates load and vibration at one support
Pulley and take-up positionsConveyor vendorFixes openings, access and local framing
Walkway width and handrail standardClient and local codeSets gallery floor width and railing loads
Maintenance access and lifting pointsOperationsFixes platforms, openings and monorail provisions
Ambient temperature and windLocal dataSets expansion joints and wind bracing
Dust and explosion classification if anyProcess and local codeSets cladding, electrical and venting provisions
Interface coordinates at both endsSite surveySets the actual line and level of the run

If the tension and drive data arrive after detailing, the gallery has to be re-detailed: the belt pulls the structure along its axis, and a frame designed only for vertical load will move.

SectionBehaviourSuitsConstraint
Truss gallery, two planesLight, stiff, economical over long spansMost belt widths on trestle runsDeep section, more fabrication labour
Plate girder gallerySimple, easy to clad and maintainMedium spans, heavy beltsHeavier per metre
Folded plate or box sectionClean appearance, good torsional stiffnessEnclosed galleries in visible areasWelding quality and distortion control
Modular pan sectionsFast site assemblyRetrofits and remote sitesMore joints to align and seal

The section follows the span and the belt, not the other way around. A wider belt with a walkway on one side needs a wider floor, and that changes the whole truss geometry.

The end of a conveyor gallery showing the truss frame, steel walkway, handrail and belt cover (illustrative concept image)

Part 4: Trestle spacing and support layout

  • Trestle spacing is a trade-off: wider spacing means fewer foundations but a deeper gallery.
  • Each intermediate support adds a foundation, a survey task and a joint to align.
  • Trestles in the belt direction must resist the pull, not only the vertical load.
  • Cross bracing in the trestle is what stops the whole run from walking sideways.
  • Support positions should avoid the drive station, the transfer tower and any live traffic route.
  • On soft ground, differential settlement between trestles shows up as belt misalignment, not as a structural crack.

Part 5: Loads that are not gravity

LoadSourceEffect on the steel
Belt tension, running and startingConveyor vendorLongitudinal pull at pulleys, take-up and anchor points
Material live load and surgeProcess designDeck and truss loading, plus impact at transfer points
Drive torque and vibrationDrive stationLocal framing, anchorage and fatigue details
Wind on a long narrow boxLocal wind dataLateral and uplift loads on trestles and gallery
Thermal movement on long runsAmbient rangeExpansion joints and sliding bearings
Dust accumulationOperationExtra dead load and cleaning access
Erection and maintenance loadsSite methodTemporary bracing and lifting points

Wind is often the governing case for an empty gallery, because the run is long, high and lightly loaded. A frame checked only for a full belt will still fail on a windy day if the trestle bracing is thin.

Part 6: Walkway, access and guarding

  • Walkway width and handrail height follow the client standard and the local code, not a default.
  • The walkway floor needs a defined drainage and cleaning method where material spills.
  • Access stairs should land outside the belt line, not into it.
  • Openings for pulleys, take-up and chutes need guarding that maintenance can remove and refit.
  • Lifting points for idler replacement should be designed, not improvised on site.
  • Emergency stops and pull cords need a route along the walkway inside the structure.
OptionAdvantagesLimitations
Open gallery with roof onlyLower cost, easy inspection, good ventilationDust blows, material gets wet
Fully enclosed with claddingWeather and dust control, cleaner appearanceCondensation, corrosion inside, access hatches needed
Enclosed with insulationNoise and heat controlHeavier cladding, detailing at joints
Open with local covers at transfersTargeted dust control at low costPartial protection only

Enclosed galleries fail at the joints: if the cladding is fixed rigidly across an expansion joint, the panels crack in the first hot season.

Part 8: Expansion joints, long runs and transfer tower interfaces

  • Long runs need expansion joints at calculated intervals, with sliding or guided bearings at the trestle tops.
  • The joint must allow movement in the run direction and resist lateral movement.
  • Cladding, walkway floor, handrails and cable trays must all break at the same joint.
  • At the transfer tower, the gallery end connects to a structure with different stiffness and different settlement.
  • Clearances at chutes and hoppers must allow movement without contact.
  • Nothing should be welded across a joint to “make it tight” on site.

Two conveyor gallery modules joined at a bolted splice above a steel trestle, with the gap kept open (illustrative concept image)

Part 9: Corrosion, abrasion and finish

  • Abrasive material wears the deck and chute liners, not only the paint.
  • Inside an enclosed gallery, condensation corrodes the underside of the roof before the outside shows anything.
  • Hot-dip galvanizing suits trestles and frames that are hard to repaint; painted systems suit visible cladding.
  • Coastal and fertilizer plants need a coating system chosen for the actual chemical exposure.
  • Wear plates, replaceable liners and inspection hatches should be designed in, not added later.

Coating system and dry film thickness depend on the corrosion category and the chemical environment on that site; they are not a single global specification.

Part 10: Tolerances and bolted splices

  • Gallery modules are spliced on site at bolted connections; the splice must be alignable, not just strong.
  • Splice positions should fall near a trestle so the joint can be supported during erection.
  • Bolt holes are drilled to a tolerance that allows site fit-up; site welding of main splices is a redesign, not a fix.
  • Camber and straightness affect belt tracking, so fabrication tolerances should be stated in the drawings.
  • Shop trial assembly of at least one bay catches splice and cladding conflicts before shipping.

Part 11: Shipping splits and module size

  • Module length is limited by container or breakbulk dimensions and by what the site crane can lift at reach.
  • Long galleries ship as several modules with marked splice pairs.
  • Truss galleries are light but bulky; breakbulk or flat rack is common for wider sections.
  • Cladding, walkway grating, handrails and bolts ship separately and must arrive in the same sequence as erection.
  • Marking must follow the erection order along the run, not the fabrication order.

Part 12: Erection over an operating plant

  • Lifting over a live belt, a road or a stockyard needs a lift plan agreed with operations.
  • Trestles are erected first, then gallery modules are landed and spliced.
  • Temporary bracing stays until the splice and the second support are connected.
  • Alignment is checked at each module, not only at the end of the run.
  • Shutdown windows can be short; modules that arrive pre-assembled with cladding partly fitted save days.

A crane lifting a conveyor gallery truss module towards prepared steel trestles while workers guide it (illustrative concept image)

Part 13: Responsibility boundary

ItemExport supplierLocal side
Structural design and detailingYes, from vendor and process dataLocal engineer reviews and stamps
Fabrication, coating, marking, packingYes—
Belt, idlers, drive and controlsNot included unless agreedConveyor vendor
Foundations and surveyAnchor bolt layout and loadsLocal civil contractor and surveyor
Erection and craneTechnical guidance and lift method inputLocal crew, crane and lift plan approval
Electrical and dust classificationProvisions onlyLocal electrical contractor and authority
Commissioning and belt trackingSupport informationConveyor vendor and operations

Part 14: Checklist before design freeze

  • Belt width, speed and material data received from the vendor.
  • Running and starting tension values confirmed.
  • Drive station location, weight and torque supplied.
  • Walkway width and handrail standard agreed.
  • Maintenance access and lifting points defined.
  • Gallery line and level surveyed at both ends.
  • Trestle spacing fixed against span and foundation cost.
  • Wind and thermal cases included in the load set.
  • Expansion joint positions and bearing types fixed.
  • Transfer tower interface and clearances checked.
  • Cladding, drainage and access hatches detailed at joints.
  • Corrosion category and coating system selected.
  • Splice positions aligned with trestles and transport limits.
  • Marking and erection sequence agreed with the site.

Part 15: Common mistakes

MistakeConsequence
Detailing before belt tension is knownGallery walks and joints open
Trestle bracing treated as optionalLateral movement under wind and starting torque
Cladding fixed across an expansion jointCracked panels in the first hot season
Splice placed mid-spanCannot be aligned or supported during erection
Walkway access opening into the belt lineUnsafe maintenance, retrofitted guarding
No drain or clean-out on the walkway floorMaterial build-up and overload
Coating chosen without chemical exposureEarly corrosion inside an enclosed gallery
Modules sized to transport onlySite crane cannot lift them at reach

Part 16: FAQ

Question: What information does a fabricator need to design a conveyor gallery? Answer: Belt width and speed, material density and lump size, running and starting tension, drive location and weight, walkway width, maintenance access, the surveyed line and level, and the local wind and temperature data.

Question: How far apart should conveyor trestles be? Answer: It is a trade-off between gallery depth and foundation count. Wider spacing needs a deeper, heavier gallery; closer spacing adds foundations, survey work and joints. The spacing is set with the belt loads and the local ground conditions.

Question: Does a conveyor gallery need expansion joints? Answer: Long runs do, because thermal movement and support settlement accumulate. Joints are placed at calculated intervals with sliding or guided bearings, and cladding, walkway and cable trays must break at the same position.

Question: Why does an empty gallery sometimes fail in wind? Answer: A long, narrow, lightly loaded box catches a lot of wind for its weight, so lateral and uplift loads can govern. Trestle bracing and anchorage must be designed for that case, not only for a fully loaded belt.

Question: Should the gallery be open or enclosed? Answer: Open with a roof suits dry material and easy inspection; enclosed suits dust, rain and appearance but needs condensation control, internal corrosion protection and access hatches. Both need the joints detailed properly.

Question: Can the gallery be shipped in container-sized modules? Answer: Often yes for narrow sections, but wider truss galleries usually go breakbulk or flat rack. Module length is limited by transport and by what the site crane can lift at reach, and splices should land near a trestle.

Part 17: Fix the belt data first

Send the belt data sheet, the drive layout, the surveyed line and level, and the walkway requirement. The gallery section, trestle spacing and joints can then be fixed before any steel is cut.